Team tasksAkram
DQA-13 — Design QA: loyalty
Review of the change request 04 screens across the apps.
| Field | Details |
|---|---|
| Task code | DQA-13 |
| Phase | P4 — V2 evolutions |
| Product scope | V2 |
| Status | Planned |
| Start | Thu 1 Apr 2027 |
| Due | Thu 1 Apr 2027 |
| Responsible | Akram — UI/UX designer |
| Co-responsible | — |
| Effort | 1 person-day(s) planned · 2 from scratch · size S |
| Area · app | Design QA · design |
| Depends on | WEB-21, MRA-21, DSH-24, DQA-12 |
| Unblocks | — |
| Milestones | V2 delivered |
Summary
Review of the change request 04 screens across the apps.
Description
Change request 04 (client loyalty document and letter of 6 Nov 2026), not yet accepted or priced by HOCO. Akram reviews RA-42 to RA-53, RW-16 to RW-18 and BO-72 to BO-83 on staging against the DES-31 frames.
Subtasks
| # | Subtask | Owner |
|---|---|---|
| 1 | Review RA-42 to RA-53 on the staging build | Akram |
| 2 | Review RW-16 to RW-18 at 1440 and 768 | Akram |
| 3 | Review BO-72 to BO-83 at 1440 and 1280 | Akram |
| 4 | File and triage issues labelled design-qa v2 | Anis |
Deliverables
- V2 loyalty design QA report
Acceptance criteria
- Every DES-31 screen is reviewed on its platform
- No blocker or major issue remains without an agreed fix
Requirements covered
| Requirement | Title | Release |
|---|---|---|
| NFR-07 | Accessibility: readable contrast, reachable buttons, consistent text sizes, explicit messages | V1 |
Test measures
- Side-by-side comparison with DES-31
KPI
- Delivered by Thu 1 Apr 2027 within 1 person-day(s).
- Every acceptance criterion above demonstrated before hand-off; linked requirements' acceptance criteria pass.
- Zero open critical defects, permission gaps or data-integrity regressions at sign-off.
Generated from content/plan/tasks.json by scripts/generate-team-tasks.mjs. Dates are computed by the scheduler (Sunday–Thursday weeks, holidays excluded) — change the plan, not this page.