DQA-13 — Design QA: loyalty

Review of the change request 04 screens across the apps.

FieldDetails
Task codeDQA-13
PhaseP4 — V2 evolutions
Product scopeV2
StatusPlanned
StartThu 1 Apr 2027
DueThu 1 Apr 2027
ResponsibleAkram — UI/UX designer
Co-responsible—
Effort1 person-day(s) planned · 2 from scratch · size S
Area · appDesign QA · design
Depends onWEB-21, MRA-21, DSH-24, DQA-12
Unblocks—
MilestonesV2 delivered

Summary

Review of the change request 04 screens across the apps.

Description

Change request 04 (client loyalty document and letter of 6 Nov 2026), not yet accepted or priced by HOCO. Akram reviews RA-42 to RA-53, RW-16 to RW-18 and BO-72 to BO-83 on staging against the DES-31 frames.

Subtasks

#SubtaskOwner
1Review RA-42 to RA-53 on the staging buildAkram
2Review RW-16 to RW-18 at 1440 and 768Akram
3Review BO-72 to BO-83 at 1440 and 1280Akram
4File and triage issues labelled design-qa v2Anis

Deliverables

  • V2 loyalty design QA report

Acceptance criteria

  • Every DES-31 screen is reviewed on its platform
  • No blocker or major issue remains without an agreed fix

Requirements covered

RequirementTitleRelease
NFR-07Accessibility: readable contrast, reachable buttons, consistent text sizes, explicit messagesV1

Test measures

  • Side-by-side comparison with DES-31

KPI

  • Delivered by Thu 1 Apr 2027 within 1 person-day(s).
  • Every acceptance criterion above demonstrated before hand-off; linked requirements' acceptance criteria pass.
  • Zero open critical defects, permission gaps or data-integrity regressions at sign-off.

Generated from content/plan/tasks.json by scripts/generate-team-tasks.mjs. Dates are computed by the scheduler (Sunday–Thursday weeks, holidays excluded) — change the plan, not this page.